Interested in learning more about the status of the Beach Renourishment Project? Find out more below:
- NORTH SEGMENT
- Complete with ~284,000 cubic yards placed
- Ian FEMA
- Ian Cat G 56,845 cubic yards
- 100% FEMA + FDEM Reimbursable
- CENTRAL SEGMENT
- ~ 85,000 of 346,000 cubic yards placed as of March 26
- ~11,000 shoreline feet remaining
- To be complete by May 31
- SOUTH SEGMENT (CWA)
- ~145,000 of 290,289 cubic yards placed as of April 2
- ~1,500 shoreline feet remaining
- To be complete by April 30
Original Plan to Fund Project Construction
- NORTH & CENTRAL
- FDEP LGFR (23LE1) ~42%
- TDC Beach Trust ILA ~43%
- Town ~15%
- SOUTH
- FDEP LGFR (23LE1) 100%
- Critical Wildlife Area
Funding To Date (Project Construction Cost $22.7M)
- HRRGP made available July 1, 2024
- TO DATE 100% of NORTH CAT G paid by FEMA/FDEM, and balance of NORTH plus CENTRAL Construction Cost by FDEP HRRGP
- $8.9M paid by HRRGP before state funds were depleted
- SOUTH SEGMENT
- 100% Construction Cost Funded by State
- ~$6.4M to be paid by State 23LE1
- REMAINING CENTRAL SEGMENT
- ~261,000 CY
- ~$5M
- 23LE1 Funded
- ~$2.1M FDEP
- ~$2.2M TDC (down from ~$4.9M)
- ~$757K TOWN
Other Notes
- Helene & Milton FEMA
- ~4,000 CY of Cat A
- Screened Overwash Sand used to rebuild berms / fill scours
- ~6,400 CY of Cat G
- Trucked Sand to Fill Scour on North End
- Cost $597,626.39